Sewer Service Letter
Formerly known as the Sewer Availability Letter, as well as the Certification Letter, this letter is for all projects that go through Santa Barbara County Planning & Development as well as the County Building Department. All projects in the County Planning phase must obtain a letter to move foward with their County Planning Permit. All projects in the County Building Department must obtain Agency Approval to obtain a County Building Permit.
The purpose of the Sewer Service Letter is to provide the County and Agent/Owner with the potential requirements and conditions that a development project must satisfy in order to receive an approval from the Montecito Sanitary District (MSD). All development projects within MSD boundaries must undergo a thorough review to ensure the integrity of the sanitary sewer system. If a project is deemed to be a Property Improvement as defined in MSD Ordinance 12, it will require approval by MSD, payment of an appropriate Connection Fee, and issuance of a Connection Permit before the County Planning & Development Department may issue the Building Permit. Any connected parcel that has building or facility remodeling, improvements, tear-down and rebuild, construction, expansion or new facility, or changes in customer classification is defined as a Property Improvement. Any improvement resulting in additional bedrooms or bathrooms, or an increase in building area of more than 350 square feet shall require a connection permit at a pro-rata connection fee.
| Permitting Stages | Agency | Typical Response Time | Project Status | |
|---|---|---|---|---|
| 1 | Property Improvements Application | County Planning | 10 - 15 business days | INTAKE |
| 2 | Project Plan Review | County Planning | 10 - 30 business days | REVIEW |
| 3 | Sewer Service Letter - Planning | County Planning | 1- 2 business days upon Letter Fee Payment | MILESTONE |
| 4 | Property Improvements Application | County Building | 10 - 15 business days | INTAKE |
| 5 | Project Plan Review | County Building | 10 - 20 business days | REVIEW |
| 6 | Sewer Service Letter - Building | County Building | 1- 2 business days upon Letter Fee Payment | MILESTONE |
| 7 | Connection Permit | MSD | 1- 2 business days upon Permit Fee Payment | REQUIRED |
| 8 | Agency Approval | County Building | Upon Connection Permit | REQUIRED |
| 9 | Inspection | MSD | 48 hours in advance | Per Permit |
| 10 | Final Occupancy | County | Upon MSD Final Inspection | COMPLETE |
To begin, head to Property Improvements Application.